[FlashMap]

Commissioning works


“Elevar” executes all activities required for putting a project into operation. In order to monitor compliance with process and getting finished product a full cycle of commissioning works is done.

Commissioning and testing are done as per procedures developed by the company with use of modern control measures.

Key points of how commissioning is done by “Elevar” are:
 
  a program of commissioning works is developed for every project on the basis of existing databases, procedures of commissioning and testing of pipelines, process equipment and utility systems;

  employees of “Elevar” participate in supervision over installation and electrical installation works thus provisioning execution of a series of measures for preparation of systems for commissioning;

  a technology is developed and equipment is produced and used for treatment of pipelines and process equipment;

  a technology is developed for quality control of installation of piggable pipelines;

  installation teams of “Elevar” deliver commissioning works with use of modern procedures of quality control of installation works. All installation works are executed in compliance with modern standards, sanitary and operational norms. Special attention is given to observation of rules and regulations of human safety.

“Elevar" employees execute the commissioning works for the following systems and equipment:

Process
equipment
  Heat supply
systems
         
Ventilation
systems
  Safety
systems
         

Electrical
equipment
 
Cooling
equipment
         

Air supply
systems
 
Water
treatment
systems
         

Automatic
control systems
 
Dispatch
systems
         

Strict observance of norms and rules of installation of highly hazardous and critical equipment:

  acceptance control of materials and accessories;

  compliance and supervision over execution of instructions provisioned by design documentation;

  timely execution of as-built documentation;

  arrangement and execution of respective checks and certifications.

 When the commissioning works are finished a package of hand-over documentation is prepared so that that the project could be accepted by State supervision authorities. Engineers and experts of “Elevar” during the commissioning works develop hand-over package of documentation including all reports from expertise, test certificates and working diagrams. All documents are prepared in strict compliance with regulations of Russian legislation and State supervision.